Blog
How do you fit RO membrane to FRP MEMBRANE house?
For the water treatment system, FRP membrane housing is one of the best options compared to PVC membrane housing and stainless steel membrane housing.
FRP MEMBRANE HOUSING is also a robust product than stainless steel membrane housing. There are different types/Sizes of membrane models. Basically, the models are in 2.5 inches, 4 inches, 8 inches and 16 inches Dia. FRP Membrane Housings are produced with 2.5” dia up to 2 elements with pressure rating from 300PSI to 1200 PSI.
FRP Membrane Housing With 4” Dia up to six elements with pressure rating from 300PSI to 1200 PSI.
FRP Membrane Housings are produced with 8” Dia up to seven elements with pressure rating from 300PSI to 1500 PSI. Sideport is available in 8″ Dia Membrane Housing.
In this article, we wish to analysis about the different membrane and their installation process.
FRP MEMBRANE HOUSING installation process:
The following is the process you need for the FRP membrane housing:
• First, you need to check the membrane model, whether it is 2.5 inches, 4 inches, or 8 inches, 16 Inches.
• Later as per the model, you need to select and fix housing.
• Next, select suitable FRP membrane housing.
• You will get an FRP membrane Housing with a fixed endcap. So you need to remove or unlock the endcap.
• Now place the “o” ring in the grove of End Cap.
• After Unlocking both the end caps you need to insert a suitable Membrane and start installing End caps as per direction of flow.
• Then, you need to apply petroleum gelly on o ring for very smooth insertion of the endcap.
• Now, you need to push that endcap with some force until it fixes in the lockplate groove.
• After that, you need to insert these lockplates/ Locking rings in the groove.
• Then, carefully fix and tighten the screws.
FRP MEMBRANE HOUSING installation process of 16 inches:
Sixteen inches model is a rare product with 2 or 3 manufacturers worldwide. In India, We are the only manufacturers by the Name of ALFA AEROSOL
The following is the process you need to for the FRP membrane housing installing process of 16 inches:
• You will get an FRP membrane Housing with a fixed endcap. So you need to remove or unlock the endcap.
• Now place the “o” ring in the grove of End Cap.
• After Unlocking both the end caps you need to insert a suitable Membrane and start installing End caps as per direction of flow.
• Then, you need to apply petroleum gelly on o ring for very smooth insertion of the endcap.
• Now, you need to push that endcap with some force until it fixes in the lockplate groove.
• After that, you need to insert these lockplates / Locking rings in the groove.
• Then, carefully fix and tighten the screws.
Explore more details about here FRP Membrane Housing.
Follow the above steps carefully to install different inches of membrane models in the FRP membrane housing.